Ministry Center Update

Ministry Center Update for the week of 4/11/11 . . . .

Great progress at the Ministry Center. 

On the office side, most of the painting is complete, ceiling grid 80% complete, bathrooms have been tiled.  Cabinets are being installed and should be complete by the end of the week. Toilet fixtures installed this week. 

On the gathering space side the sheetrock and taping is complete.  Painting will begin tomorrow and should be complete by the end of the week.  All of the light fixtures should be installed by the end of next week. 

It looks like we are still on schedule to have the building complete by the end of the month, hopefully moving in by mid-May.  We still have a lot of work to do to get the parking lot complete so pray for warm, dry weather.  Have a great week!

Roger Stroh, Ministry Center Project Manager