Ministry Center Update

Ministry Center Update for week of 3/1/11 . . . .

 Work continues to progress at the Ministry Center.  All framing is complete and inspections passed.  Electrical work is 50% complete.  All of the sheetrock should be complete by the end of this week.  Duct work is also close to completion.  The next 2 weeks we will be pulling cable, wires, etc and putting in the furnaces and water heater.  Thanks for all the volunteer help.

Roger Stroh, Ministry Center Project Manager