The weather has been good and we have seen good progress this week.  All of the footings for the ministry center have been poured.  The foundation walls have been started and will be complete by the middle of next week.  Our garage roof was almost completed this past weekend.  We hope to have it finished within the next week.  Thanks for your continued support!

Roger Stroh, Ministry Center Project Manager